Construction Management and General Contracting

Projects

Sacramento Railyards Track Relocation Project Sacramento, CA

The project consists, in general, of relocating approximately 2.4 miles of heavy rail; construction of passenger track and platforms, passenger tunnel, pedestrian tunnel, service tunnel; utility modifications and new utilities (which includes a new 42-inch water main); and providing pedestrian access from the existing depot building to the new platforms within the Sacramento Valley Station. The project includes phased construction and requires coordination with other contracts. CPM provides scheduling and office engineering services on this project. Sacramento Railyards West Tunnel Ramps Project Sacramento, CA The project consists, in general, of constructing two ramps, and stairways. The scope of work includes ramp water proofing, excavation and handling of impacted soil, controlling ground water and stabilizing soil, lighting/electrical, backfill, drainage, and SWPPP and related work.

The project includes phased construction and requires coordination with other contracts. CPM provides scheduling and office engineering services on this project.

Client/Agency: City of Sacramento
Cost: $42M and $3M, respectively
Services Provided: Scheduling and office engineering services.